The City reconstructed Fire Station 41 in northern Overland Park in 2024.
The original fire station (The Marty Memorial Station) reached the end of its designed 50-year life span. The new Fire Station 41 addresses design best practices for equipment and personnel, accommodates larger equipment and allows for the implementation of cancer-reducing measures. The new station will continue to serve the northern portion of Overland Park for generations to come.
Land acquisition, design, and construction of Fire Station 41 were included in the Capital Improvements Program. The overall budget for the project was $13,225,000.
Tony Rome
Facilities Engineer & Project Manager
[email protected]
913-895-6001
Alan Long
Fire Chief
[email protected]
913-895-8451
The new facility at 7550 W. 75th Street is built on land from the old fire station along with a portion of newly acquired land adjoining the existing plot.
Prior to the demolition of the original fire station, the City renovated the decommissioned Marty Pool house to use as a temporary fire station during construction. This allowed fire crews to provide the same level of responsiveness to emergency calls within the district. Learn more about the Marty Pool/Park conversion on the Marty Pool webpage.
The City works toward minimizing its environmental impact through a variety of efforts and initiatives to ensure Overland Park is a sustainable city.
In July 2022, City Council approved the addition of solar panels to the design of Fire Station 41, increasing the project’s overall budget by $175,000. Solar panels installed on the fire station’s roof power approximately 75 percent of the building. Once Clean Energy Tax Credits are applied, the City expects to recoup the cost of design and installation through energy savings over 10 years.
City staff held an open house meeting to share the vision for the project and seek input from neighbors and residents on May 31, 2022 at the American Legion Post 370 at 7500 W.75th Street. The purpose of the May 31, 2022 neighborhood meeting was to share the vision for the project and seek neighbors’ input prior to Planning Commission consideration of the special use permit application at its June 13 meeting.
The Planning Commission approved a special use permit for the project at its June 13, 2022 meeting and a final development plan for the project at its August 8, 2022 meeting.
The City broke ground at the site of the new fire station on March 29, 2023.
Construction concluded in early summer 2024, and the new facility is open!
Take a look inside the new Fire Station 41!